Rugged Acres

SUPERVISORS APPROVE SOITEC’S RUGGED SOLAR PROJECT IN BOULEVARD

 

Photo: SOITEC panel at Newberry Springs, similar to panels approved for Boulevard.

By Miriam Raftery

October 16, 2015 (Boulevard) – By a 4 to 1 vote with only Supervisor Dianne Jacob opposed, the Board of Supervisors this week approved a revised version of the controversial Rugged Acres industrial solar facility and rescinded approval of an earlier plan.

A judge had tossed out the original environmental impact review because massive battery storage facilities were added after public comment was closed.  Supervisors approved a revamped plan with the energy storage facility removed.

Supervisor Jacob stated, “I strongly support solar but I believe it belongs on rooftops of both single family homes and businesses and a solar farm in the right location,” Jacob said. “This project would potentially industrialize our back country which was never meant to be. The project can no longer live up to the promises and major use findings that are needed for approval.”


Error message

Support community news in the public interest! As nonprofit news, we rely on donations from the public to fund our reporting -- not special interests. Please donate to sustain East County Magazine's local reporting and/or wildfire alerts at https://www.eastcountymedia.org/donate to help us keep people safe and informed across our region.

JUDGE OVERTURNS COUNTY APPROVALS OF SOITEC BOULEVARD PROJECTS

 

Update, August 21, 2015:  Donna Tisdale notified us that the backcountry "celebration over the death of Soitec's Boulevard projects was a bit premature. Today, County staff informed me that Soitec is going to remove the 160 cargo containers full of potentially toxic batteries from their Rugged Solar project and will resubmit the revised EIR for certification by the Board of Supervisors. (Back in February, Soitec self-terminated their Tierra Del Sol Solar project just 1 month after receiving Board approval due to a lack of buyers.) Staff is trying to docket the revised EIR for the Board agenda by October so they can meet the Court's order to report back by November 2nd on how they plan to comply," adds Tisdale, who concludes, "The battle to save the backcountry continues."

 

By Miriam Raftery

Photo: A Soitec solar panel in Newbury Springs, California

August 20, 2015 (Boulevard) – The last of four massive solar projects proposed by Soitec Solar in Boulevard may now be officially dead.

On August 7th, Superior Court Judge Joel R. Wohlfeil  overturned County Supervisors’ approvals of Soitec’s Rugged Acres and Tierra del Sol projects,  because the approvals violated the California Environmental Quality Act (CEQA)  Soitec and the County failed to file an appeal by the August 14th deadline, says Donna Tisdale, chair of the Boulevard Planning Group and founder of Backcountry Against Dumps, which filed the lawsuit aiming to halt the project. View the court's judgment.

“Soitec’s Boulevard projects, approved for 1,200 acres, are now dead and buried!” Tisdale wrote in an email to project opponents. Any new projects proposed for those sites would need to start all over at step one,” requiring a new environmental impacts review, a lengthy and costly process. “I have asked the County for details on when they will set aside their voided approvals, as mandated by the court,” Tisdale added.


Error message

Support community news in the public interest! As nonprofit news, we rely on donations from the public to fund our reporting -- not special interests. Please donate to sustain East County Magazine's local reporting and/or wildfire alerts at https://www.eastcountymedia.org/donate to help us keep people safe and informed across our region.